Newswire

Tag: fuel load

First fuel load at Kakrapar-4 announced

October 30, 2023, 7:00AMNuclear News
The Kakrapar nuclear power plant. (Photo: India’s Department of Atomic Energy)

The initial loading of nuclear fuel into the Kakrapar-4 reactor core has begun, the Nuclear Power Corporation of India Ltd. has announced. Permission for fuel load was granted by India’s Atomic Energy Regulatory Board “after carrying out stringent safety and security reviews,” according to the NPCIL.

Slovakia adds fifth reactor to nuclear fleet

October 23, 2023, 7:55AMNuclear News
Slovakia’s Mochovce nuclear plant, located about 62 miles east of Bratislava, the nation’s capital. (Photo: Slovenské Elektrárne)

The Unit 3 reactor at Slovakia’s Mochovce nuclear power facility has completed the commissioning process, becoming a full-fledged member of the country’s nuclear fleet, plant owner Slovenské Elektrárne has announced.

Bruce-6 connected to grid after refurbishment

September 15, 2023, 9:30AMNuclear News
Bruce Power operations staff synchronizes Unit 6 to the Ontario electrical grid on September 8. (Photo: Bruce Power)

The ongoing major component replacement (MCR) project at Ontario’s Bruce nuclear power plant reached another milestone last Friday with the reconnection to the grid of the facility’s Unit 6 reactor. According to a release from plant operator Bruce Power, the work was completed ahead of schedule and on budget despite the challenges of the COVID-19 pandemic.

Vogtle-4 fuel load started

August 18, 2023, 12:58PMNuclear News
The Vogtle-4 reactor cavity in July. (Photo: Georgia Power)

Georgia Power has begun the process of loading fuel into the Vogtle plant’s Unit 4 reactor, the company announced yesterday, marking another pivotal milestone toward commercial operation of the second of the facility’s two new units.

Bruce-6 nears a return to service

August 9, 2023, 9:30AMNuclear News
The Bruce nuclear power plant in Ontario, Canada. (Photo: Bruce Power)

Unit 6 at the Bruce nuclear power plant in Kincardine, Ontario, achieved a sustained fission chain reaction over the weekend—a key step in returning the 817-MWe CANDU reactor to commercial operation, Bruce Power announced yesterday.

Vogtle-3 begins commercial operation

July 31, 2023, 12:39PMNuclear News
Vogtle-3 (Photo: Georgia Power)

To the ears of the nuclear community, the news from Georgia Power this morning may sound a bit like “Ode to Joy” from Beethoven’s Ninth: After years of delay, Unit 3 at the Vogtle nuclear power plant has entered commercial operation, becoming the first newly constructed power reactor in the United States in more than 30 years and the nation’s first Westinghouse-supplied Generation III+ AP1000 unit to be placed into service. The new unit joins Vogtle-1 and -2—1,169-MWe four-loop pressurized water reactors that entered commercial operation in the late 1980s.

Southern Nuclear given go-ahead for Vogtle-4 fuel load

July 31, 2023, 10:41AMNuclear News
The Vogtle-4 control room. (Photo: Georgia Power)

The Nuclear Regulatory Commission has authorized Southern Nuclear Operating Company to begin loading fuel into Unit 4 at the Vogtle nuclear expansion site near Waynesboro, Ga., making the unit the second reactor to reach this milestone in the agency’s combined license process—a little less than one year after Vogtle-3. (Prior to 1989, reactors were licensed under a two-step process, requiring both a construction permit and an operating license.)

All ITAACs for Vogtle-4 completed

July 24, 2023, 9:30AMNuclear News
Vogtle’s Unit 4 reactor in June. (Photo: Georgia Power)

Southern Nuclear, operator of Georgia’s Vogtle plant, has informed the Nuclear Regulatory Commission that all 364 inspections, tests, and analyses for Unit 4 have been performed, and all acceptance criteria for the new reactor have been met. Primary plant owner Georgia Power made the announcement last Friday.

Hot functional testing completed at Vogtle-4

May 3, 2023, 3:00PMNuclear News
The Vogtle-4 turbine building in March. (Photo: Georgia Power)

Georgia Power has announced another key milestone for the Vogtle nuclear expansion project near Waynesboro, Ga.—the completion of hot functional testing at Unit 4. This achievement marks another significant step toward commercial operation for the Generation III+ AP1000 reactor, which is projected to enter service late in the fourth quarter 2023 or in the first quarter 2024.

Vogtle-3 connects to grid

April 3, 2023, 12:00PMNuclear News
Vogtle Units 3 and 4 in February. (Photo: Georgia Power)

Unit 3 at the Vogtle nuclear power plant has been successfully synchronized and connected to the electric grid, Georgia Power announced on April 1. The unit—one of two Westinghouse-supplied AP1000s at the Waynesboro, Ga., plant’s nuclear expansion site—becomes the first new U.S. power reactor to start up in seven years.

Vogtle-3 fuel load has begun

October 14, 2022, 12:01PMNuclear News
Vogtle Unit 3 in September. (Photo: Georgia Power)

Georgia Power announced this morning that fuel loading at Vogtle-3 has commenced, marking an important milestone on what has proved to be a long and bumpy road to startup and commercial operation of the first new nuclear power reactors to be built in the United States in more than three decades. (Major work on the Vogtle-3 and -4 project began in 2012, with a price tag of $14 billion and scheduled unit start dates of 2016 and 2017. The project’s total cost is now expected to exceed $30 billion.)

More adjustments to Vogtle milestone dates likely

January 13, 2021, 3:08PMNuclear News

The initial shipment of nuclear fuel for Unit 3 arrives at the Vogtle site in December. Photo: Georgia Power

Largely as a result of the continuing COVID-19 crisis, the Vogtle reactor-construction project team expects to further adjust dates for achieving key project milestones, including the start of hot functional testing and fuel load for Unit 3, Southern Company subsidiary Georgia Power announced on January 11.

The company added, however, that it continues to expect to bring Unit 3 into service this November and Unit 4 into service in November 2022. Additional updates on the project will be provided during Southern’s quarterly earnings call next month.

Vogtle project team reports delays, holds to approved start dates

October 28, 2020, 9:46AMNuclear News

In testimony filed last week with the Georgia Public Service Commission, Georgia Power and Southern Nuclear acknowledge that the “aggressive” target dates set in July for some of the Vogtle construction project’s upcoming milestones have had to be pushed back by a few months. At the same time, however, the companies continue to express confidence in being able to meet the regulatory-approved commercial start dates for the new reactors—November 2021 for Unit 3 and November 2022 for Unit 4.

The testimony was filed in support of Georgia Power’s Twenty-third Semi-annual Vogtle Construction Monitoring Report, released in August, which covers the period from January 1 to June 30, 2020.